IEEE 802.5 Current Activities

Current Committee Timetable

Task Date Actual
Date
Status
First unapproved draft[Secure] 100 MBit/s Token Ring available for committee discussion 31-Oct-97 31-Oct-97 Complete
Tutorial on HSTR at 802 Evening Session 11-Nov-97 11-Nov-97 Complete
HSTR PARs (802.5t, 802.5u, 802.5v) approved by 802.5 Working Group 12-Nov-97 13-Nov-97 Complete
Agreement reached on Technical Approach for 100 Mbit/s token ring 13-Nov-97 13-Nov-97 Complete
HSTR PARs (802.5t, 802.5u, 802.5v) approved by 802 SEC 13-Nov-97 13-Nov-97 Complete
Strawman 0.5[Secure] 100 Mbit/s token ring circulated for comments 21-Nov-97 27-Nov-97 Complete
Comment period on 100 Mbit/s Strawman closed 31-Dec-97 7-Jan-98 Complete
Earliest approval of 3 HSTR PARs (t, u and v) by NESCOM Dec-97 9-Dec-97 Complete
802.5 Interim meeting to resolve issues with 100 Mbit/s Strawman 14 to 16-Jan-98 13 to 16-Jan-98 Complete
Start of 802.5t (HSTR) Draft 1 [Secure] Ballot 28-Jan-98 30-Jan-98 Complete
End of 802.5t (HSTR) Draft 1 Ballot 08-Mar-98 - Complete
IEEE Plenary meeting, Irvine CA 09 to 13-Mar-98 - Complete
Start of 802.5t (HSTR) Draft 2 [Secure] Ballot 01-Apr-98 30-Mar-98 Complete
Formation of ballot pool for LMSC ballot of 802.5t 01-Apr-98 01 to 30 Jul-98 Complete
End of 802.5t (HSTR) Draft 2 Ballot 10-May-98 10-May-98 Complete
Interim meeting 'ff' 12 to 15-May-98 - Complete
802.5t (HSTR) draft 2.1 pre-release 10-Jun-98 10-Jun-98 Complete
802.5t/draft 2.1B re-circulation ballot start 08-Jun-98 19-Jun-98 Complete
End of 802.5t/draft 2.1B Re-circulation ballot 24-Jun-98 05-Jul-98 Complete
IEEE Plenary meeting, La Jolla CA 6 to 10-Jul-98 - Complete
Forward 802.5t (HSTR) to LMSC and ISO for balloting 09-Jul-98 04-Sep-98 Complete
802.5v/strawman 0.2 ballot start 17-Jul-98 16-Jul-98 Complete
802.5t/draft 2.2 re-circulation ballot start 30-Jul-98 30-Jul-98 Complete
End of 802.5t/draft 2.2 Re-circulation ballot 11-Aug-98 17-Aug-98 Complete
End of 802.5v/strawman 0.2 ballot 17-Aug-98 - Complete
Interim meeting 'gg' 24 to 28-Aug-98 - Complete
802.5t/draft 2.3 re-circulation ballot start 26-Aug-98 - Complete
End of 802.5t/draft 2.3 re-circulation ballot 07-Sep-98 - Complete
Submit 802.5t for LMSC ballot 08-Sep-98 - Complete
802.5t for LMSC ballot 11-Sep to 19-Oct-98 - Complete
Plenary meeting 'HH' 9 to 13-Nov-98 - Complete
Start of 802.5w (Errata) Draft 1 [Secure] Ballot 01-Dec-98 02-Dec-98 Complete
End of 802.5w (Errata) Draft 1 Ballot 04-Jan-99 11-Jan-99 Complete
802.5t LMSC recirculation ballot 15-Dec-98 - Complete
Interim meeting 'hh' 18 to 22-Jan-99 - Complete
802.5t LMSC recirculation ballot closes 22-Jan-99 - Complete
802.5t 2nd LMSC recirculation ballot closes 05-Mar-99 - Complete
Plenary meeting 'II' 8 to 12-Mar-99 - Complete
802.5t forwarded to RevCom by 802 SEC 11-Mar-99 - Complete
802.5v/D1 starts initial committee letter ballot 02-Apr-99 01-Apr-99 Complete
802.5w/D1.1 starts committee 15-day recirculation ballot 02-Apr-99 03-Apr-99 Complete
802.5w/D1.1 recirculation ballot closes 19-Apr-99 03-May-99 Complete
802.5v/D1 committee letter ballot closes 03-May-99 12-May-99 Complete
Copenhagen interim meeting 'ii' 10 to 12-May-99 - Complete
802.5v/D1.1 starts recirculation committee letter ballot 26-May-99 - Complete
802.5v/D1.1 committee letter ballot closes 25-Jun-99 - Complete
802.5t approved by IEEE Standards Board 26-Jun-99 - Conditional approval
Montréal plenary meeting 'JJ' 5 to 9-Jul-99 - Complete
802.5v/D1.2 starts 15-day recirculation committee letter ballot 22-Jul-99 23-Jul-99 Complete
802.5v/D1.2 committee letter ballot closes 6-Aug-99 7-Aug-99 Passed unanimously
802.5w/D1.2 LMSC sponsor electronic letter ballot opens 18-Aug-99 18-Aug-99 Complete
802.5w/D1.2 LMSC sponsor electronic letter ballot closes 17-Sep-99 17-Sep-99 Complete
Hilo, Hawaii plenary meeting 'KK' 8 to 12-Nov-99 - Complete
802.5w/D1.3 LMSC sponsor electronic recirculation letter ballot opens 09-Dec-99 09-Dec-99 Complete
802.5w/D1.3 LMSC sponsor electronic recirculation letter ballot closes 19-Dec-99 19-Dec-99 No comments
802.5v/D1.3 LMSC sponsor electronic letter ballot opens 15-Dec-99 22-Dec-99 Complete
802.5v/D1.3 LMSC sponsor electronic letter ballot closes 26-Jan-2000 26-Jan-2000 Complete
802.5z/D1 starts 30-day committee letter ballot 24-Dec-99 24-Dec-99 Complete
802.5z/D1 committee letter ballot closes 31-Jan-2000 31-Jan-2000 Complete
Albuquerque plenary meeting 'LL' 6 to 10-Mar-2000 - -